The capital
works programmes proposed for the above period are detailed
below in:
| PROJECT |
SUBURB |
BUDGET
ALLOCATION |
| ROAD REHABILITATION |
|
$4,512,000 |
| KANANGRA DRIVE - Various Sections |
GWANDALAN |
|
| STREET TREES |
VARIOUS |
|
| HUTTON ROAD Stage 1 - Paris Apartments
to Stewart
Street |
NTH ENTRANCE |
|
| LONG JETTY TRAFFIC MANAGEMENT PLAN WORKS |
T/ENT LONG JETTY |
|
| HUE HUE ROAD - Various Section |
JILLIBY |
|
| BUNDEENA/ BERKELEY RD - Intersection Upgrade |
GLENNING VALLEY |
|
| BOUNDARY ROADS WITH GOSFORD - Dog Trap Road - 50/50 Gosford |
OURIMBAH |
|
| BATEAU BAY EAST
- T.M.P. Works Continuation |
BATEAU BAY |
|
| LINDSAY STREET - Stage 1 |
SHELLY BCH |
|
| SWADLING STREET - continuation |
LONG JETTY |
|
| THE RIDGEWAY - 50/50 with Gosford |
TUMBI UMBI |
|
| THE CORSO - Start |
GOROKAN |
|
| STANLEY STREET - Kaye
Ave to Stelling
Ave |
KANWAL |
|
| POLLOCK AVE - Council's Share of Funds |
WYONG |
|
| BRUSH ROAD - West
Bend |
OURIMBAH |
|
| BERKELEY ROAD - Pedestrian refuge near high school |
BERKELEY VALE |
|
| SHIRLEY ST/COACHWOOD DVE - Traffic calming devices |
OURIMBAH |
|
| EASTERN ROAD (TUMBI
ROAD)+SHERRY Stg1 |
TUMBI UMBI |
|
| BANGALORE STREET - Seal gravel road |
OURIMBAH |
|
| LAKEDGE AVENUE - Stage 1 - start |
BERKELEY VALE |
|
| BUDGEWOI TOWN CENTRE - Additional Works |
BUDGEWOI |
|
| ROADS TO RECOVERY |
|
$904,000 |
| TUMBI ROAD /EASTERN ROAD - Roundabout |
TUMBI |
|
| MINOR RDS. REHAB. PROGRAM |
|
$400,000 |
| DUNCAN STREET |
THE ENTRANCE |
|
| St. JAMES AVENUE |
BERKELEY VALE |
|
| STANLEY STREET (nth end) |
KANWAL |
|
| MERMAID DRIVE |
BATEAU BAY |
|
| GLADYS AVE |
BERKELEY VALE |
|
| YARRAMALONG RD - Flat section near eastern
cemetery |
|
|
| SEC. ROAD CONST - SECTION 94 |
|
|
| LINK ROAD CONSTRUCTION - stage 1 |
WARNERVALE |
$8,000,000 |
| LOUISIANA ROAD/WARNERVALE ROAD SIGNALS |
WARNERVALE |
$121,000 |
| TOUKLEY TOWN CENTRE
CARPARK |
TOUKLEY |
$200,000 |
| THE ENTRANCE STREETSCAPE IMPROVEMENTS |
THE ENTRANCE |
$198,000 |
| GOORAMA AVENUE OVERBRIDGE |
SAN REMO |
$850,000 |
| JOHNSON ROAD/PACIFIC HWY INTERSECTION |
TUGGERAH |
$253,000 |
| THE ENTRANCE /LONG JETTY TRAFFIC MANAGEMENT
SCHEME |
THE ENTRANCE |
$1,522,000 |
| WARNERVALE ROAD OVER CULVERT |
HAMLYN TERRACE |
$379,000 |
| WARNERVALE ROAD BUS SHELTERS |
WARNERVALE |
$67,000 |
| MINNESOTA/WARNERVALE ROAD ROUNDABOUT |
HAMLYN TERRACE |
$418,000 |
| CRAIGIE AVENUE/ PACIFIC
HIGHWAY INTERSECTION |
KANWAL |
$229,000 |
| MATARAM RD MID BLOCK AND EXTENSION SIGNALS |
WOONGARRAH |
$300,000 |
| DRAINAGE CONST. - SECTION 94 |
|
|
| WARNERVALE ROAD WATER QUALITY FACILITY A1/B6 |
WARNERVALE |
$909,000 |
| TUGGERAH STGE3 WETLAND NO2 CONSTRUCTION |
TUGGERAH |
$200,000 |
| TUGGERAH STGE 3 WETLAND NO 3 CONSTRUCTION |
TUGGERAH |
$215,000 |
| WARNERVALE ROAD CULVERT |
HAMLYN TERRACE |
$330,000 |
| WARNERVALE ROAD WATER QUALITY FACILITY B1 |
WARNERVALE |
$568,000 |
| TUGGERAH LAND ACQUISITION FOR DETENTION
BASIN |
TUGGERAH |
$12,000 |
| F3 DETENTION
BASIN |
MARDI |
$650,000 |
| TUGGERAH STGE 3 WETLAND NO1 CONSTRUCTION |
TUGGERAH |
$330,000 |
| CULVERTS AT PACIFIC HWY |
TUGGERAH |
$350,000 |
| OPEN CHANNEL - railway- meridian channel |
TUGGERAH |
$215,000 |
| DRAINAGE |
|
$3,020,000 |
| SAN REMO AREA
- Continuation |
SAN REMO |
|
| BUDGEWOI AREA - Continuation |
BUDGEWOI |
|
| OAKLAND AVE/ASHTON AVE - Stge 3 |
THE ENTRANCE |
|
| HUTTON RD with roadworks |
NTH ENTRANCE |
|
| ENVIRONMENTAL- WETLANDS incl. Lake
Mac. Projects |
|
|
| REPAIR GREENACRE DRAIN |
LAKE MUNMORAH |
|
| LAKEDGE AVENUE with roadworks |
BERKELEY VALE |
|
| NETWORK REHAB. |
|
|
| STANLEY ST - No 10/16 |
GOROKAN |
|
| LINDSAY STREET with roadworks |
SHELLY BCH |
|
| SWADLING STREET with roadworks |
LONG JETTY |
|
| THE CORSO with roadworks |
GOROKAN |
|
| MISCELLANEOUS MINOR CAT 1 PROJECTS |
|
|
| ASPLEY CRT WETLAND
- Council's Share of funds |
BLUEHAVEN |
|
| CHAIN VALLEY BAY
NORTH - various works |
CVB NORTH |
|
| GEORGE EVANS RD - No4 |
BATEAU BAY |
|
| TOOWOON BAY/ARCHBOLD ROAD
- Stage 1 |
TOOWOON BAY |
|
| EASTERN ROAD with
roadworks |
BATEAU BAY |
|
| WATSON AVENUE |
TUMBI |
|
| STANLEY STREET with roadworks |
KANWAL |
|
| BATEAU BAY PUBLIC SCHOOL - Brooke
Ave |
BATEAU BAY |
|
| RESERVE DRIVE |
BATEAU BAY |
|
| LAKEDGE AVE - culverts near Thomas Walker |
BATEAU BAY |
|
| RESEALING PROGRAM |
|
|
| LOCAL |
|
$2,100,000 |
| REGIONAL 3X3 COMPONENT & BLOCK GRANT |
|
$315,000 |
| RTA - OTHER FUNDING |
|
|
| BLOCK GRANT (maintenance proportion) |
|
$80,000 |
| TRAFFIC FACILITIES |
|
$247,000 |
| HEAVY PATCHING |
|
|
| MAINTENANCE |
|
$150,000 |
| RESEALS |
|
$300,000 |
| |
|
|
| |
TOTAL |
$450,000 |
| RTA IMPROVEMENT PROGRAM |
Various |
est.$1586000 |
| |
MR335,336,509 |
|
| REGIONAL RDS REHABILITATION |
|
RTA $ WSC $ |
| CHITTAWAY ROAD - CH 0 T0 CH 0.385 |
OURIMBAH |
$119,000 $119,000 |
| ENTERPRISE DRIVE - West of Turpentine Bridge |
OURIMBAH |
$30,000 $30,000 |
| ENTERPRISE DVE - 330m west of Turpentine
Bridge |
OURIMBAH |
$45,000 $45,000 |
| |
|
|
| |
TOTAL |
$194000 $194000 |
| RTA B.SPOT/IMPROVEMENT PROJECTS
- assumed |
|
|
| To be finalised |
|
|
| |
TOTAL |
$0 |
| CARES Facility - RTA Funding |
|
$0 |
| WSC Maintenance. Funds (50/50 with Gosford) |
|
$15,000 |
| WSC Construction Funds -Separate Line Item No 4.1.10 |
|
$136000 |
| BRIDGE REFURBISHMENT |
|
$300,000 |
| Edwards Creek Bridge |
DOORALONG |
|
| CONSTRUCTION OF CARPARKS |
|
$78,000 |
| Sandy Beach |
SUMMERLAND PT. |
|
| Soldiers Pt - bottom carpark and entry road
- Caravan park funded |
|
|
| FOOTPAVING |
|
$420,000 |
| Bellevue Road - Stage 1 |
TUMBI UMBI |
|
| Winbin Crescent |
GWANDALAN |
|
| Mossman Avenue |
BATEAU BAY |
|
| Short Street |
THE ENTRANCE |
|
| Fravent Street |
TOUKLEY |
|
| Scenic Drive |
BUDGEWOI |
|
| Tumbi Creek Road |
BERKELEY VALE |
|
| Cresthaven Avenue |
BATEAU BAY |
|
| Marlowe Road |
BATEAU BAY |
|
| Wallarah Road |
KANWAL |
|
| KERB & GUTTER INFILL |
|
|
| Sycamore St - 6 Frontages |
|
$85,000 |
| PEDESTRIAN PROTECTION - upgrade refuges
to standard |
|
$50,000 |
| Bay Village Road refuge at Leagues club |
BATEAU
BAY |
|
| Anne Findlay PL |
BATEAU
BAY |
|
| Kanangra Drive - opposite the swim school |
GWANDALAN |
|
| Park Rd - Footpaving Works |
THE ENTRANCE |
|
| ROUNDABOUT ADJUSTMENTS |
|
$100,000 |