The capital
works programmes proposed for the above period are detailed
below in:
Rolling Works Programme 2001/2002 Table A
Rolling
Works Programme 2002/2003 Table B
Rolling
Works Programme 2003/2004 Table C
Rolling
Works Programme 2004/2005 Table D
Rolling
Works Programme 2005/2006 Table A
Rolling
Works Programme 2006/2007 Table B
Rolling
Works Programme 2007/2008 Table C
Rolling
Works Programme 2008/2009 Table D
Table C Road
Rehabilitation/Drainage 2007/2008
| PROJECT |
SUBURB |
BUDGET
ALLOCATION |
| ROAD REHABILITATION |
|
$4,425,000 |
| KANANGRA DRIVE - Various Sections |
GWANDALAN |
|
| WATKINS STREET / ELSIEMERE - 1b |
LONG JETTY |
|
| STREET TREES |
VARIOUS |
|
| CHITTAWAY ROAD in front of shops |
CHITTAWAY BAY |
|
| SUNRISE AVENUE |
BUDGEWOI |
|
| BRUSH ROAD |
OURIMBAH |
|
| HUE HUE ROAD - Various
Sections |
JILLIBY |
|
| FAIRPORT AVENUE/ DENING
ST +FOOTPATH IN FAIRPORT |
THE ENTRANCE |
|
| MALVINA PARADE - Stage 1 |
LAKE HAVEN |
|
| ELOORA ROAD - Stage 2 |
LONG JETTY |
|
| PANORAMA PARADE - Stage 5 |
CHARMHAVEN |
|
| LONG JETTY TRAFFIC MANAGEMENT PLAN WORKS |
THE ENTRANCE LONG JETTY |
|
| BUSH STREET - Stage 1 - Continuation |
NORAH HEAD |
|
| |
|
|
| ROADS TO RECOVERY |
|
$904,000 |
| LINDSAY STREET - Stage 3 |
SHELLY BCH |
$400,000 |
| LAKEDGE AVENUE - Stage 2 |
BERKELEY VALE |
$504,000 |
| |
|
|
| |
TOTAL |
$904,000 |
| MINOR RDS. REHAB. PROGRAM |
|
$1,000,000 |
| OLEANDER STREET - ROWENA TO LILLIAN + SECTS. |
NORAVILLE |
|
| MARINA STREET |
BUDGEWOI |
|
| BLENHEIM AVENUE |
BERKELEY VALE |
|
| ALEXANDRA STREET |
BUDGEWOI |
|
| FIRST AVENUE |
TOUKLEY |
|
| WINDSOR ROAD |
BERKELEY VALE |
|
| BUCKINGHAM ROAD |
BERKELEY VALE |
|
| LAKEWAY DRIVE |
LAKE MUNMORAH |
|
| MINOR RDS. REHAB. PROGRAM
(Contd) |
|
|
| PAUL PLACE |
GOROKAN |
|
| LAKESHORE AVENUE |
C V BAY |
|
| NATUNA AVENUE |
BUDGEWOI |
|
| EDWARD STREET |
BUDGEWOI |
|
| RESTLEA AVENUE |
CHARMHAVEN |
|
| McGIRR AVENUE |
THE ENTRANCE |
|
| CAMBRIDGE CLOSE |
OURIMBAH |
|
| GASCOIGNE ROAD |
GOROKAN |
|
| NAELCM AVENUE |
KILLARNEY VALE |
|
| ANCHOR AVENUE |
TOUKLEY |
|
| HAMMOND ROAD |
TOUKLEY |
|
| MURRAWAL ROAD |
WYONGAH |
|
| SEC. ROAD CONST - SECTION 94 |
|
|
| MATARAM RD |
WOONGARRAH |
$2,680,000 |
| MATARAM RD / HIAWATHA
RD INTERSECTION |
WOONGARRAH |
$100,000 |
| PACIFIC HIGHWAY PEDESTRIAN OVERPASS |
HAMLYN TERRACE |
$631,000 |
| PACIFIC HIGHWAY / MATARAM RD SEAGULL INTERSECTION |
WOONGARRAH |
$2,000,000 |
| PEDESTRIAN OVERPASS 2 SPARKS RD WEST OF MINNESOTA RD |
HAMLYN TERRACE |
$1,472,000 |
| WARNERVALE ROAD BUS SHELTERS |
WARNERVALE |
$50,000 |
| WARNERVALE RD NOT CULVERT SECTION |
HAMLYN TERRACE |
$951,000 |
| PACIFIC HWY PED FACILITY NORTH OF JOHNS RD |
WADALBA |
$274,000 |
| PACIFIC HWY / JOHNS
RD / POLLOCK
AVE |
WYONG |
$1,833,000 |
| BUS SHELTERS ETC |
WARNERVALE |
$744,000 |
| DRAINAGE CONST. - SECTION
94 |
|
|
| |
|
|
| DRAINAGE |
|
$3,020,000 |
| LAKEDGE AVENUE with roadworks |
BERKELEY VALE |
|
| MALVINA PARADE with roadworks |
LAKEHAVEN |
|
| SAN REMO AREA
Continuation |
SAN REMO |
|
| BUDGEWOI AREA Continuation |
BUDGEWOI |
|
| ENVIRONMENTAL- WETLANDS incl. Lake
Mac. Projects |
|
|
| NETWORK REHABILITATION |
|
|
| ELOORA ROAD - Stage 2 with roadworks |
LONG JETTY |
|
| DONALD AVENUE No37 |
KANWAL |
|
| LAUREN AVENUE |
LAKE MUNMORAH |
|
| GILBERT STREET NOS 5&6 - Stage2 |
LONG JETTY |
|
| MISCELLANEOUS MINOR CAT 1 PROJECTS |
|
|
| TURNER CLOSE |
BLUEHAVEN |
|
| CADONIA RD -Tuggerawong
Rd to school with roadworks |
TUGGERAWONG |
|
| McLACHLAN AVE - Stage 2 |
LONG JETTY |
|
| LINDSAY STREET with roadworks |
SHELLY BCH |
|
| RESEALING PROGRAM |
|
RTA REG $ WSC $ |
| LOCAL |
|
$2,000,000 |
| REGIONAL 3X3 COMPONENT & BLOCK GRANT |
|
$315,000 |
| |
|
|
| RTA - OTHER FUNDING |
|
|
| BLOCK GRANT (maintenance proportion) |
|
$80,000 |
| TRAFFIC FACILITIES |
|
$247,000 |
| |
|
|
| HEAVY PATCHING |
|
|
| MAINTENANCE |
|
$150,000 |
| RESEALS |
|
$300,000 |
| |
|
|
| |
TOTAL |
$450,000 |
| |
|
|
| RTA IMPROVEMENT PROGRAM |
Various |
est.$1700000 |
| |
MR335,336,509 |
|
| |
|
|
| REGIONAL RDS REHABILITATION |
|
RTA $ WSC $ |
| To be finalised |
|
|
| |
TOTAL |
|
| |
|
|
| RTA B.SPOT/IMPROVEMENT
PROJECTS - assumed |
|
|
| To be finalised |
|
|
| |
TOTAL |
$0 |
| CARES Facility - RTA
Funding |
|
$0 |
| WSC Maintenance Funds (50/50 with Gosf.) |
|
$15,000 |
| |
|
|
| BRIDGE REFURBISHMENT |
|
$300,000 |
| Bridge St |
OURIMBAH |
|
| Teralba Road Bridge |
OURIMBAH |
|
| Mandalong Rd No1 |
MANDALONG |
|
| |
|
|
| CONSTRUCTION OF CARPARKS |
|
$78,000 |
| Berkeley Vale Football Oval |
BERKELEY VALE |
$38,000 |
| Baker Park Wyong
- Adjacent to pump station |
WYONG |
$40,000 |
| |
TOTAL |
$78,000 |
| |
|
|
| FOOTPAVING |
|
|
| |
|
$420000 |
| |
|
|
| KERB & GUTTER INFILL |
|
|
| To be finalised |
|
$85,000 |
| |
|
|
| PEDESTRIAN PROTECTION -
upgrade refuges to standard |
|
$50,000 |
| |
|
|
| ROUNDABOUT ADJUSTMENTS |
|
$100,000 |